On September 21, 2017, Khmelnitsky-1 operates at a capacity of 660 MW. Over the past day, the power unit generated 15.74 million kWh of electricity, and 313.91 million kWh of electricity has been generated since the beginning of the month.

Khmelnitsky-2 has been in outage for 25 days.
On August 27, 2017, Khmelnitsky-2 was disconnected from the grid for middle maintenance.

Radiation situation on the site and adjacent areas has not changed, and remains at the level corresponding to normal operation of power units, and does not exceed natural background values.
Information Centre of SE KhNPP