Daily Information on Khmelnitsky NPP Operation

2017-11-14

415

#

On November 14, Khmelnitsky-1 has been in outage for eight days. On November 7, 2017, Khmelnitsky-1 was disconnected from the grid for middle maintenance, which should be completed in 96 days.

Khmelnitsky-2 operates at 1010 MW power. Over the past day, the power unit generated 24.29 million kWh of electricity, and 315.59 million kWh of electricity has been generated since the beginning of the month.

Radiation situation on the site and adjacent areas has not changed, and remains at the level corresponding to normal operation of power units, and does not exceed natural background values.

Фото: Євген Цибульський
Information Centre of SE KhNPP